A lot of land outside the cities is still held on a certificate of use, a Nor Sor 3 Gor or an older Nor Sor 3, rather than a full title deed (chanote). Owners and buyers ask the same thing: can it be upgraded, how, how long does it take and what does it cost? This guide answers from the Land Code itself and from the Department of Lands' own procedure and fee table, read on 16 November 2026. Our guide to Thai title deeds explains the document types first if they are new to you.

The short answer

The person named on the certificate can apply at the land office where the land lies for a title deed for that plot under section 59 of the Land Code, or wait for a ministerial section 58 ter program that converts certificates in a whole area. An individual application goes through a survey with neighbors notified, a 30 day public announcement, and signing by the land officer. The Department of Lands puts the processing at 83 days, plus a 15 to 200 day wait for the survey. The official fees are small; the survey expenses set by the province are the main cost. Mortgages and leases on the old certificate carry over to the chanote.

Upgrading a certificate of use at a glance
PointThe ruleWhere it is written
Individual applicationThe person with the right of possession may apply for one plot, whether or not a section 58 survey announcement exists; issued when the officer considers it appropriateLand Code, section 59
Area conversionMinister announces the area in the Royal Gazette at least 30 days ahead; map made from the aerial photo evidence without a new survey unless neededLand Code, section 58 ter
Who gets the deedUnder 58 ter, the person named as holding the right in the certificate of useLand Code, section 58 ter
Mortgages, leases, other entriesCopied onto the new title deedLand Code, section 59 quater
The old certificateCancelled and returned to the land officer, unless lostLand Code, sections 58 ter and 59 quinquies
ObjectionsLand officer mediates; provincial land officer decides; court within 60 daysLand Code, section 60
Time83 days, not counting a 15 to 200 day wait for the surveyDepartment of Lands citizen's manual
01

What does upgrading a Nor Sor 3 Gor actually mean?

The Land Code calls the Nor Sor 3 family a certificate of use (nangsue rap rong kan tham prayot) and the chanote a title deed (chanote thi din). Upgrading means asking the land office to issue a title deed for land that today has only a certificate of use. Once the deed is issued, the old certificate is cancelled: section 59 quinquies says that when a title deed is issued under section 58 bis or section 59 the old land document is cancelled and must be returned to the land officer, unless it has been lost, and section 58 ter says the same for an area conversion from the date set for handing out the deeds (Land Code).

The Department of Lands lists the Nor Sor 3, Nor Sor 3 Gor and Nor Sor 3 Khor among the documents that support an application for a title deed, alongside older evidence such as the possession notice (Sor Kor 1), reservation certificates and settlement documents (Department of Lands). Its own procedure for issuing a certificate of use has the owner point out the plot on an aerial photograph map sheet (Ror Wor 10 Gor) as its second step, which is why the Land Code has a separate route for certificates drawn on those sheets.

There are two routes, and which one fits depends on whether you want to act now for one plot or whether the Ministry is running a program in your area.

Aerial view of green rice fields divided by a palm-lined track and a dirt road
02

What are the two routes in the Land Code?

Route 1: an individual application (section 59). Where a person with the right of possession applies for a title deed or certificate of use for their own plot, whether or not there is a ministerial announcement under section 58, the officer issues it under the rules of the Code when the officer considers it appropriate. The person with the right of possession includes someone who has occupied and used the land in succession from the person who held the possession evidence (Land Code, section 59). This is the route for an owner who wants the chanote now.

Route 2: an area conversion (section 58 ter). When the Minister considers it appropriate to issue title deeds for land with certificates of use drawn on aerial photograph map sheets in a given area, the Minister announces the area and the start date in the Royal Gazette at least 30 days ahead. The map for the deeds is made by adjusting the aerial photo evidence used for the certificates, without a new survey, unless the land officer finds a survey necessary. From the start date, registrations that need a survey are suspended for those certificates in the area, unless the land officer allows one in a necessary case. The deed is issued to the person named as holding the right in the certificate. When a plot's deed is ready, the land officer announces the date for handing it out, and the certificate counts as cancelled from that date (Land Code, section 58 ter).

A third provision, section 58, covers a full survey program for a whole province; the Minister announces the province and year, the governor posts the area and start date at least 30 days ahead, and owners walk the surveyors round their land. If such a program reaches your district, joining it is another way to get a deed. Section 59 bis is for people who occupied land before the Land Code came into force with no land document and no possession notice, so it is not the route for a certificate holder.

03

What documents do you need to apply?

The Department of Lands' citizen's manual for an individual application where there is a land document lists, for an individual (Department of Lands manual):

A company files its registration certificate, memorandum, shareholder list and a meeting resolution or minutes on the application; a power of attorney, if one is used, is signed by the authorized directors. The manual notes that ID, house registration, marriage, divorce and death records, and company records from the Department of Business Development, are now mainly drawn from linked government databases. Our guide to power of attorney in Thailand explains how to appoint someone if you live abroad.

04

How does an individual application work, step by step?

The Department of Lands sets out 15 steps for an individual title deed application (Department of Lands). In plain terms:

  1. Take a queue ticket and point out the plot on the land office map sheet.
  2. File the application, give a statement and pay the fees.
  3. The survey section books a survey date and assigns a surveyor.
  4. The office finds the adjoining owners, prints notices to them and hands you the notices to serve; you pay the survey deposit and collect the boundary markers.
  5. The surveyor goes out, surveys the plot and checks how the land has been used.
  6. The office calculates the area and draws the deed map.
  7. The land officer announces the issue of the title deed for 30 days. One copy is posted at the land office, the district office, the municipal or subdistrict office and the kamnan's office for the area.
  8. Where needed: the governor's approval (for land with no possession notice, or over 50 rai, under section 59 bis); a check by the land inspection committee under Ministerial Regulation No. 43, as amended by No. 59, for land in a forest conservation zone; or coordination with the Agricultural Land Reform Office or the settlement manager for land in a land reform zone, self-help settlement or cooperative settlement.
  9. The land officer signs the deed, and you are called to collect it.

The application is filed at the provincial land office, branch or sub-office for the area where the land lies, Monday to Friday 08:30 to 16:30 with a lunch break, except official holidays (Department of Lands manual). Our land office guide covers the visit itself.

Surveyor in a high-visibility vest standing behind a tripod instrument on a cleared plot
05

How long does the upgrade take?

The citizen's manual breaks the work into stages: 1 day to check documents, 15 to 200 days of survey waiting, then stages of 30, 11, 40 and 1 days. It states the total processing time as 83 days, not counting the survey wait of 15 to 200 days, and says each land office's survey wait can be checked in its monthly survey report (Ror Wor 19) (Department of Lands manual).

The manual lists the cases that are not counted in that time. Plan for longer if any of these apply:

06

What does it cost?

The official fees are fixed and small. The survey expenses depend on the province. From the Department of Lands manual (Department of Lands manual):

Fees and expenses for an individual title deed
ItemAmount
Application5 baht per plot
Announcement10 baht per plot
Witnessing the application20 baht
Power of attorney, if used20 baht per matter, plus a 30 baht duty stamp
Title deed fee50 baht for up to 20 rai; 2 baht for each rai above 20
Survey fee40 baht per plot for a title deed
Boundary markers15 baht each
Officials' transportAt the rate the province announces
Survey workersAt the Ministry of Finance rate for the province
Local administrative official50 baht a day
Other items, for example serving notices100 baht

The Department's knowledge page gives the same application, announcement, survey and boundary marker fees and adds a 10 baht a plot payment to the person who posts the announcement (Department of Lands). Because the transport and labor lines vary, ask the land office for its estimate when you file; the survey deposit is paid before the surveyor goes out. The fees for a later sale, gift or mortgage of the land are a different table, covered in property transfer fees.

07

What if a neighbor objects?

The neighbors are part of the process from the start: the land office searches for the adjoining owners, prints notices to them and has the notices served before the survey (Department of Lands). The 30 day announcement then gives anyone with a claim a chance to come forward.

If someone disputes the right, section 60 of the Land Code sets the path (Land Code, section 60):

  1. The officer or land officer investigates and tries to settle it. If the parties agree, the land office proceeds as agreed.
  2. If they do not agree, the provincial land officer (or branch provincial land officer) decides and notifies both sides in writing.
  3. The side that disagrees must file a case in court within 60 days of learning of the order. If a case is filed, the land office waits for the final judgment. If no case is filed in time, it proceeds as the provincial land officer ordered.

Where the new survey gives a different area from the old possession notice, section 59 ter says the officer issues the document for the area actually used. Boundary questions with neighbors are covered in our boundary survey guide, and long-term occupation by someone else in our guide to adverse possession.

08

What happens to mortgages, leases and restrictions?

Registered rights carry over. Section 59 quater says that when a title deed is issued under section 58 bis, 58 ter or 59, any encumbrances recorded on the old land document, and any change of the person holding the right registered while the deed is being prepared, are copied onto the new title deed (Land Code, section 59 quater). A bank mortgage, a registered lease, a usufruct or a servitude on the Nor Sor 3 Gor therefore appears on the chanote. Tell your lender before you apply.

During an area conversion, some registrations pause. Under section 58 ter, from the start date in the Minister's announcement, registrations that need a survey (such as a subdivision) are suspended for certificates in the area, unless the land officer allows one in a necessary case. The suspension names only registrations that need a survey.

The ten-year ban does not come with the upgrade for a certificate holder. Section 58 bis bars transfer for ten years only for a person in its paragraph two (3), someone who occupied and used the land after the Land Code came into force without a reservation certificate (bai jong), occupation permit (bai yiap yam) or evidence of a right under the law on allocating land for living. Inheritance is excepted, as are transfers to a political subdivision, a government organization or a state enterprise set up by Act, and a transfer to a cooperative to settle a debt with the cooperative registrar's approval. A holder of a certificate of use is in paragraph two (1) (Land Code, section 58 bis). A restriction already printed on your own certificate, for example on land allocated by the state, is separate and must be read on the document. Our guide to title deed encumbrance checks shows how to read the register.

09

What should buyers and foreign owners check?

This page is limited to the Land Code and the Department of Lands texts named in the sources. It does not list which areas currently have a section 58 ter program, and it does not cover lenders' policies on land with a certificate of use.

FAQ

Frequently asked questions

How do you upgrade a Nor Sor 3 Gor to a chanote in Thailand?

There are two routes in the Land Code. Under section 59 the person with the right in the land can apply at the land office for a title deed for that one plot, whether or not a ministerial survey announcement covers the area, and the land office issues it when it considers it appropriate. Under section 58 ter the Minister can announce an area where title deeds will be issued for land with certificates of use drawn on aerial photograph map sheets, and the land office then issues deeds plot by plot, usually by adjusting the aerial photo evidence rather than resurveying. Under section 58 ter the chanote goes to the person named as holding the right in the certificate; under section 59 the applicant is the person with the right of possession, which includes someone who has occupied and used the land in succession from a person who held the possession notice evidence.

How long does it take to turn a Nor Sor 3 Gor into a chanote?

The Department of Lands citizen's manual for an individual application under section 59, where there is a land document, puts the processing at 83 days in all, not counting the wait for the survey, which it gives as 15 to 200 days depending on the land office. The 83 days also exclude cases with an objection that has to be investigated, a check by the land inspection committee for land in a forest conservation zone, interpretation of aerial photographs, waiting for other agencies, or doubt about the plot's position.

How much does it cost to upgrade a Nor Sor 3 Gor to a chanote?

The official fees are small: 5 baht for the application per plot, 10 baht for the announcement per plot, 20 baht for witnessing the application, a 40 baht survey fee per plot, 15 baht per boundary marker, and a title deed fee of 50 baht for up to 20 rai plus 2 baht for each rai above that, according to the Department of Lands manual. The larger part of the bill is the survey expenses: officials' transport at the rate the province announces, survey workers at the Ministry of Finance rate for the zone, 50 baht a day for the local administrative official, and items such as 100 baht for serving notices. Ask the land office for its estimate when you file.

What documents do I need to apply?

For an individual the Department of Lands lists the ID card, house registration, marriage certificate and any proof of a change of name, the original land document (here the Nor Sor 3 Gor or Nor Sor 3), land tax receipts or other related evidence, and any further evidence the officer asks for in advance. If someone files for you, the power of attorney must say the attorney may give statements and sign for incomplete documents. Heirs bring the death certificate, will or court order appointing the administrator. Companies add their registration papers and a meeting resolution or minutes on the application.

Do the neighbors have to sign?

The neighbors are notified. The Department of Lands steps for an individual title deed include searching for the names of adjoining owners, printing notices to them and serving those notices before the surveyor goes out. If someone objects to the boundary or the right, section 60 of the Land Code lets the land officer investigate and mediate. If the parties cannot agree, the provincial land officer decides, and the side that disagrees must sue in court within 60 days of learning of the order, or the land office proceeds as ordered.

What happens to the mortgage or lease on my Nor Sor 3 Gor?

It carries over. Section 59 quater of the Land Code says that when a title deed is issued under sections 58 bis, 58 ter or 59 and the old land document has encumbrances recorded on it, or a change of rights is registered while the deed is being prepared, those entries are copied onto the new title deed. Your bank's mortgage or a registered lease therefore moves to the chanote with the land.

Is there a ban on selling the land after it gets a chanote?

Not because of the upgrade itself, in the cases this page covers. The ten-year transfer ban in section 58 bis of the Land Code applies only to a person in its paragraph two (3): someone who occupied and used land after the Land Code came into force with no reservation certificate (bai jong) or occupation permit (bai yiap yam) and no evidence of a right under the law on allocating land for living. A holder of a certificate of use falls under paragraph two (1). Any restriction already written on your certificate, such as land allocated by the state, is a separate question to check on the document itself.

Can a foreigner apply to upgrade a Nor Sor 3 Gor?

The applicant is the person who holds the right in the certificate of use, or their attorney. A foreigner generally cannot hold land in Thailand in their own name, so in practice the application is made by the Thai owner, for example a Thai spouse, or by an attorney they appoint. See our guides to whether foreigners can own land and to buying property with a Thai spouse before you rely on any arrangement.

Ask a question

Didn’t find your answer above? Ask below -- real questions help us decide what to write next.

Keep going
Property EducationThai Title DeedsLand Office GuideBoundary Survey GuideAdverse PossessionEncumbrance ChecksCan Foreigners Own LandProperty Transfer FeesBuilding Permits

Find land and homes in Thailand

Compare houses, villas and land for sale, listed by partnered agents.

Browse residencesThe buying process

General information only, not legal advice. This page summarizes the Thai text of the Land Code and Department of Lands publications in our own words; the official text is the authority. Ask the land office where the land lies about your plot. BAANLYY never takes paid placement.

By the BAANLYY Editorial Team
Last updated 16 November 2026 · Last checked 16 November 2026
Sources

Sources

Official primary sources are listed above with the date we last checked them. Thai rules, fees, thresholds and procedures change and can be applied differently by individual offices and embassies, confirm the current requirement with the responsible authority before relying on it. General information only, not legal, tax or medical advice. BAANLYY never takes paid placement in editorial content.

New to Thailand? BAANLYY can help with:
Visa helpRelocationInvesting helpCorporate housing

Have a question BAANLYY can help with?

Planning a move, a rental or an investment in Thailand? Tell us what you need, visa, housing, relocation, the numbers, and our team points you the right way. No obligation.

Add at least one way to reach you. *

Free tools for this

Start with a free tool

All Tools & Calculators