When you hire a builder or a renovation contractor in Thailand, the contract sits on top of twenty-one sections of the Civil and Commercial Code on hire of work. They decide who supplies tools and materials, when you can end the job for delay, how long the contractor answers for defects, when the price is due and who carries the loss if the work is destroyed before handover. This guide sets them out from the Thai text.
The hire of work title of the Civil and Commercial Code, sections 587 to 607. Section 587 defines hire of work as a contract in which one person, called the contractor, agrees to carry out a piece of work to completion for another person, and that other person agrees to pay remuneration for the result of the work. Building a house, adding a floor, fitting out a condo and replacing a roof all fit that description. In this guide the person who orders the work is called the client, and the remuneration is called the price.
| Question | Default rule in the Code | Section |
|---|---|---|
| Who supplies the tools | The contractor | 588 |
| Quality of materials the contractor supplies | Must be of good quality | 589 |
| Can the client inspect during the work | Yes, at any time while the work is going on | 592 |
| Contractor starts late or falls behind | The client may terminate without waiting for the delivery date | 593 |
| Work is heading for a defective result through the contractor's fault | Notice to put it right within a reasonable time; after that a third party can repair or continue at the contractor's risk and cost | 594 |
| Late delivery | Reduction of the price, or termination where time is of the essence | 596 |
| Late or defective delivery | The client may withhold the price unless the contractor gives proper security | 599 |
| How long the contractor answers for defects | Defects appearing within one year of delivery, or five years for a structure on the ground other than a wooden building, unless the contract says otherwise | 600 |
| Deadline to sue over a defect | One year from the day the defect appeared | 601 |
| When the price is due | On acceptance of the work, or of each part where parts are priced separately | 602 |
| Ending the contract before completion | The client may terminate at any time on paying compensation | 605 |
| Subcontracting | Allowed unless the contract turns on the contractor's personal skill; the contractor stays liable | 607 |
Source: Civil and Commercial Code, Book III, Title VII, sections 587 to 607, Thai consolidated text on the Office of the Council of State law search, read on 16 November 2026.
Only one of these sections says in its own words that the contract can change it: section 600 on the defect periods opens with the words unless otherwise provided in the contract. This guide does not go beyond the text to say which of the other rules a contract can or cannot change, and it does not cover consumer protection law or the Building Control Act. For permits see the guide to building permits in Thailand, and for budgets the guide to the cost of building a house.
Four short sections divide responsibility for what goes into the job.
Section 591 cuts both ways. If you buy the tiles, the steel or the roofing yourself, or you instruct a change on site, a defect that comes from that choice is yours unless the contractor knew better and stayed silent. A contractor who sees a problem with what the client has supplied or instructed is expected to say so.
Where the contractor supplies the materials, section 595 adds that liability for defects is governed by the provisions of the Code on sale. Those are set out in the section on defects below.
The Code does not make a client wait for the handover date to act.
Inspection (section 592). The contractor must allow the client, or the agent of the client, to inspect the work at any time while it is being carried out. An engineer, architect or other person you appoint can therefore go on site for you.
Termination for delay before the deadline (section 593). The client is entitled to terminate the contract, without having to wait for the time fixed for delivery, in any of three situations:
Work heading for a defective result (section 594). Where, while the work is going on, it can be foreseen with certainty that it will be finished in a defective way or contrary to the terms of the contract through the fault of the contractor:
Both sections reward a paper trail. A dated notice that names the defect and fixes a reasonable period is the step section 594 describes, and photographs and site reports are how you show later that the delay was not your fault. The home renovation contract checklist lists the records worth keeping.

Section 596 covers the contractor who delivers after the time fixed in the contract or, where the contract fixes no time, after a reasonable time has passed. The client is entitled to a reduction of the price. Where time is of the essence of the contract, the client is entitled to terminate instead.
Section 597 is the trap on the client side. If the client accepts the work without reservation, the contractor is not liable for the delay in delivery. A client who intends to claim for lateness therefore has to say so when taking the work over, and it is safer to say it in writing.
The Code itself does not set a daily penalty for delay. A fixed sum per day of delay, where there is one, comes from the contract. This guide covers only what the hire of work sections provide when the contract is silent.
Four sections work together: acceptance, the liability period, the deadline to sue, and concealment.
| Point | What the Code says | Section |
|---|---|---|
| Accepting defective work | If the client accepts the work with its defects, expressly or impliedly, without reservation, the contractor is not liable, unless the defect could not be discovered at the time of acceptance or the contractor concealed it | 598 |
| Liability period, general | Only defects that appear within one year from the day of delivery, unless the contract provides otherwise | 600 |
| Liability period, structures on the ground | Defects that appear within five years, where the work is a structure on the ground other than a wooden building, unless the contract provides otherwise | 600 |
| Concealed defects | The one and five year limits do not apply where it appears that the contractor concealed the defect | 600, second paragraph |
| Deadline to sue | No action may be brought against the contractor more than one year after the defect appeared | 601 |
| Withholding the price | Allowed where the work is delivered with defects, unless the contractor gives proper security | 599 |
Source: Civil and Commercial Code, sections 598 to 601, read on 16 November 2026.
Read sections 600 and 601 as two separate clocks. The first asks when the defect showed itself: within one year of delivery for most work, or within five years for a structure on the ground that is not a wooden building. The second starts on the day the defect appeared and gives one year to bring the claim. On our reading, a crack that appears in the fourth year of a concrete house is inside the five year period, but the claim still has to be filed within one year of the day it appeared.
Section 600 begins with the words unless otherwise provided in the contract, so the contract can set different periods. Check what yours says before you rely on the one and five year figures.
Where the contractor supplied the materials (section 595). Liability for defects is then governed by the provisions of the Code on sale. The three sections on defects in sale read for this guide say:
How the sale sections and sections 598 to 601 fit together on a given job is a question for a lawyer; this guide prints the text of each and goes no further. Defects in a home bought from a developer or a previous owner are a sale, not hire of work, and are covered in the guide to seller liability for property defects. For the day of handover itself, use the house defect warranty checklist.
Section 602 sets the starting point: the price is payable when the work is accepted. If the work is to be delivered in parts and a price is stated for each part, the price for each part is payable when that part is accepted.
That is the logic behind staged payments on a house build. A schedule that ties each payment to a part of the work, such as foundations, structure, roof and finishes, with an amount stated for each, puts the contract inside the second paragraph of section 602. The Code sets no percentages and no deposit; those figures are whatever the contract says.
Section 599 gives the client one lever. Where the work is delivered late or delivered with defects, the client is entitled to withhold the price, unless the contractor gives proper security. The section does not say how much may be withheld, so keep what you hold back in proportion to the delay or defect, and record your reasons in writing at the time.
A fire, a flood or a collapse part way through a build raises the question of who pays to start again. The Code answers by asking who supplied the materials.
| Who supplied the materials | Who bears the loss | Is the price payable | Section |
|---|---|---|---|
| The contractor | The contractor, provided the loss was not caused by an act of the client | No | 603 |
| The client | The client, provided the loss was not caused by an act of the contractor | No, unless the loss was caused by an act of the client | 604 |
Source: Civil and Commercial Code, sections 603 and 604, read on 16 November 2026. Both sections apply where the work is destroyed or damaged before it has been properly delivered.
Neither section mentions insurance. Whether the site is insured during the build, and who must buy that cover, is a matter for the contract and the insurer.

The hire of work title gives four routes out.
Section 605 is written for the client only; the title contains no matching section that lets a contractor walk away at will. What a contractor can do when a client does not pay is governed by the contract and by the general rules of the Code on obligations, which were not read for this guide.
Section 607 allows the contractor to give the whole of the work, or part of it, to a subcontractor. The exception is a contract whose essence is the personal skill of the contractor. In every case the contractor remains liable for any conduct or fault of the subcontractor.
For a client this means two things. Your claim for the electrician or the roofer who did poor work is against the contractor you hired, under your contract. And if you chose a builder for their own craft, the contract should say so in plain words, because that is what brings the exception in section 607, and the rule in section 606, into play.
Section 600 of the Civil and Commercial Code says that, unless the contract provides otherwise, the contractor is liable only for defects that appear within one year from the day of delivery, or within five years where the work is a structure on the ground other than a wooden building. The limit does not apply where the contractor concealed the defect. Section 601 then bars an action against the contractor more than one year after the defect appeared.
Section 599 says that where the work is delivered late or delivered with defects, the party who ordered the work is entitled to withhold the remuneration, unless the contractor gives proper security. Section 602 sets the normal rule: remuneration is payable when the work is accepted, or part by part where the work is to be delivered in parts with a price stated for each part.
Section 593 allows the party who ordered the work to terminate without waiting for the delivery date if the contractor does not start in proper time, delays contrary to the terms of the contract, or delays through no fault of that party so that it can be foreseen the work will not be finished within the agreed time.
Section 605 says that for as long as the work is not finished, the party who ordered it may terminate the contract on paying the contractor compensation for any damage arising from the termination.
Under section 598, a contractor is not liable where the work was accepted with its defects, expressly or impliedly, without reservation, unless the defect was one that could not be discovered at the time of acceptance or the contractor concealed it. Under section 597, accepting the work without reservation also ends liability for late delivery.
Section 607 lets the contractor give the whole or part of the work to a subcontractor, unless the essence of the contract is the personal skill of the contractor. The contractor remains liable for any conduct or fault of the subcontractor.
See what a house costs to build in Thailand, or find a contractor in your city.
General information only, not legal advice. Rules are from the Civil and Commercial Code, Book III, Title VII, hire of work (sections 587 to 607), with sections 472 to 474 on defects in sale, read in Thai in the consolidated text on the Office of the Council of State law search on 16 November 2026. Consumer protection law, the Building Control Act and court rulings are not covered. A written contract can set different terms where the law allows; confirm with a lawyer before you sign or stop paying.
Official primary sources are listed above with the date we last checked them. Thai rules, fees, thresholds and procedures change and can be applied differently by individual offices and embassies, confirm the current requirement with the responsible authority before relying on it. General information only, not legal, tax or medical advice. BAANLYY never takes paid placement in editorial content.