Answer first

Do not begin fit-out work on drawings or verbal consent alone. Confirm permitted use, landlord and building approval, required authority filings, contractor documents, utility capacity, safety procedures, insurance, work hours, completion evidence and reinstatement terms in writing.

A fit-out in Thailand can need up to three separate approvals, and each one comes from a different place. The landlord approves the works under the lease and the Civil and Commercial Code. The local official approves them under the Building Control Act if the works modify the building or change what it is used for. And the business itself may need its own filing before it opens, as a restaurant does under the Public Health Act. This guide sets out what each source says, as we read it on 15 November 2026, and ends with a checklist you can print.

ApprovalWho gives itWhere the rule is
Consent to alter or add to the premisesThe landlordCivil and Commercial Code, section 558, and the lease
Permit or notification to modify a buildingThe local officialBuilding Control Act B.E. 2522, sections 21 and 39 bis
Permit or notification to change the use of a buildingThe local officialBuilding Control Act, sections 32 and 33
License or certificate of notification for a food placeThe local officialPublic Health Act B.E. 2535, section 38
Electricity supply in the tenant's nameThe Metropolitan or Provincial Electricity AuthorityEach authority's application conditions
02

When does a fit-out need a building permit?

When the work modifies the building. Section 21 of the Building Control Act B.E. 2522 says that any person who will construct, modify or move a building must obtain a permit from the local official, or notify the local official and proceed under section 39 bis. Section 4 defines modify as changing, adding to, increasing, reducing or enlarging the character, extent, design, shape, proportion, weight or area of the structure or of the other parts of a building already built so that it differs from the original, where the work is not a repair or a modification set out in a Ministerial Regulation.

That last phrase is where most interior fit-outs are decided. A Ministerial Regulation lists the works that are not treated as modification. We could not open its current text, and it has been amended, so this guide does not repeat its thresholds. Have the architect or engineer state in writing whether the scope is a modification, and confirm it with the local office if the work touches structure, floor loading, floor area, fire escape routes or the facade.

The notification route. Under section 39 bis a person may modify a building without applying for a permit by notifying the local official on the prescribed form. The notification must name the architect responsible for the design and the engineer responsible for the design and calculation, each holding a professional license, and the works supervisors, and must include copies of their licenses and the site plan, drawings, specifications and calculations signed by the designers.

Who the local official is. The Act names the Governor of Bangkok for Bangkok, the mayor for a municipality and the Mayor of Pattaya City for Pattaya. A Bangkok Metropolitan Administration district office guide for the application to construct, modify or demolish a building gives a processing time of 45 days, and notes that the time may be extended no more than twice, by no more than 45 days each time, with written notice to the applicant. The guide is undated, so confirm the time and the current fee with the office itself. Our guide to building permits in Thailand goes through the Act, the two routes and the fees in full.

The penalty. In the text we read, section 65 sets imprisonment of up to three months, a fine of up to 60,000 baht, or both, for a breach of section 21, plus a daily fine of up to 10,000 baht for as long as the breach continues.

03

Does a change of use need approval?

It can. Section 32 of the Building Control Act lists controlled-use buildings: buildings used as a warehouse, hotel, condominium or medical facility, and buildings used for commerce, industry, education, public health or other business as a Ministerial Regulation prescribes. When construction or modification of such a building is finished, the permit holder notifies the local official in writing so the work is inspected within thirty days, and the local official issues a certificate if the work matches the permit or notification.

The same section says the owner or occupier of a controlled-use building may not use it, or allow anyone to use it, for a business other than the one stated in the permit or notification. Section 33 adds that a building which is not a controlled-use building may not be used for a section 32 business without a permit from, or a notification to, the local official, and that the same applies when a controlled-use building is changed from one business to another.

For a tenant this means two questions for the landlord before signing: what use is the building permitted for, and can we see the certificate. If your business is a different use from the last tenant's, ask who will apply for the change and who pays.

04

Which documents should be approved?

Put one approval file together and have the landlord sign against it. If the works need a permit or a notification, the same drawings go to the local official.

  • drawings and specifications, each with a number, revision and date;
  • structural and services changes, with the engineer's calculation where load or structure changes;
  • contractor and insurance records;
  • building access plan: working hours, lifts, deliveries, noise and waste;
  • authority submissions where required, with the receipt or permit number;
  • the landlord's signed consent letter that lists all of the above.
05

How do power and other services get approved?

Settle the electrical load before the design is final, because a larger supply involves the electricity authority as well as the landlord. The Metropolitan Electricity Authority serves Bangkok, Samut Prakan and Nonthaburi. Its page for a juristic person applying for electricity at premises where the company is not registered asks for the identity document of the authorized director, a document showing ownership of the premises, for which its examples include a lease with evidence of the lessor's ownership or a letter of consent to use the premises, and a certificate for the internal wiring and electrical equipment installation. It says a new juristic applicant is placed in tariff type 2, small business, and may later be placed in another type depending on the pattern of use.

Elsewhere, the Provincial Electricity Authority's conditions say the applicant may be the owner of the land or premises, a person with the owner's written consent, a person with a right to occupy under a contract such as a lease, or the operator of a business at the premises. For a juristic person it lists the company registration certificate issued within the last six months, the identity card of the authorized person, the house or building registration, and evidence of ownership or right of possession.

Neither page we read states a processing time, and neither covers raising the size of an existing meter, so ask the local office. Our utility capacity checklist covers what to measure first.

Row of round electrical back boxes set into a freshly plastered wall before sockets are fitted
06

What fire rules apply once staff move in?

A fit-out fixes where the exits, alarms and extinguishers go, so design to the workplace rule from the start. The Ministerial Regulation on fire prevention and suppression in the workplace B.E. 2555, issued under the Occupational Safety, Health and Environment Act B.E. 2554, was given on 7 December 2012. We did not check for later amendments. As published, it says:

  • Clause 3: every workplace posts a notice of fire-fighting and evacuation instructions where it can be clearly seen.
  • Clause 4: a workplace with ten or more employees also has a fire prevention and suppression plan, kept at the workplace for the safety inspector.
  • Clause 5: where several workplaces share one building, every employer in it shares the duty to provide the fire system and the plan.
  • Clause 8: at least two escape routes on every floor, able to take all employees to a safe point within five minutes and kept free of obstruction. Doors on escape routes open in the direction of escape and close by themselves. Sliding doors, roller shutters and revolving doors are not allowed on them, and they may not be locked while employees are working.
  • Clause 9: a fire alarm system on every floor where the workplace is in a building of two or more stories or has an area of 300 square meters or more.
  • Clause 13: portable extinguishers matched to the class of fire, placed where they are clearly visible, and inspected at least once every six months.
  • Clauses 27 and 30: at least 40 percent of employees in each unit trained in basic fire fighting, and a fire and evacuation drill for all employees at least once a year.

Separately, section 32 bis of the Building Control Act makes the owners of high-rise, extra-large and public assembly buildings, and other buildings a Ministerial Regulation names, have an inspector check the structure and the electrical, alarm, fire and other systems and report to the local official. Ask the landlord to confirm that your design does not change anything that inspection covers. See also our property fire safety checklist.

07

What changes for a restaurant or cafe?

The food business needs its own filing with the local official, on top of the landlord's consent and any building permit. Section 38 of the Public Health Act B.E. 2535, as quoted in a Department of Health legal opinion of 20 February 2019, says a person who will set up a food-selling place or food-storage place in a building or area of more than 200 square meters, and which is not selling in a market, must obtain a license from the local official. Where the area is 200 square meters or less, the person must notify the local official before setting up, in order to receive a certificate of notification. Section 48, quoted in the same document, has the official issue a receipt that serves as temporary evidence until the certificate is issued.

Because the threshold is floor area, decide early how the kitchen, storage and seating are measured, and ask the local office what it needs to see on the drawings. Check too that the lease permits a food use and that the landlord accepts the exhaust, grease and drainage design, since those are alterations under section 558.

08

Which taxes sit on the contractor's agreement?

Three Revenue Department rules touch a fit-out contract. None of them is an approval, but each needs a line in the agreement.

  • Stamp duty. Item 4 of the Stamp Duty Schedule is hire of work: 1 baht for every 1,000 baht or fraction of the remuneration. The schedule names the contractor as the person liable. Our stamp duty guide explains how it is paid.
  • Withholding tax. Clause 8 of Revenue Departmental Order No. Tor Por 4/2528 says a company, juristic partnership or other juristic person that pays income from hire of work or service to the payees it lists shall withhold income tax at 3.0 percent. Clause 12/7 applies the duty where the agreement value is 1,000 baht or above, whether or not it is paid in installments of less than that.
  • Value added tax. The Revenue Department's VAT page, last updated 23 November 2020, states that the general rate is currently 7 percent. Say in the agreement whether the price includes it. Our VAT guide has more.
09

What should completion include?

Completion is the point where the fit-out becomes part of the record of the premises, so close it out on paper as well as on site.

  • inspection and testing of electrical, air conditioning, plumbing and fire systems;
  • as-built records that show what was actually installed;
  • warranties and manuals from the contractor and suppliers;
  • defect schedule with a date for each item;
  • signed handover between contractor and tenant, and the landlord's written acceptance of the works;
  • where the building is a controlled-use building and a permit or notification was needed, the written notice to the local official and the certificate under section 32.
10

What happens to the fit-out when the lease ends?

Unless the lease says otherwise, expect to hand the unit back as you received it. Section 561 of the Civil and Commercial Code says that if no written description of the condition of the property was made and signed by both parties, the tenant is presumed to have received it in a good state of repair, and must return it in that condition when the contract ends, unless the tenant can prove it was out of repair at delivery. Section 562 makes the tenant liable for loss or damage caused by the tenant's own fault, or by the fault of people living with the tenant or of a subtenant, but not for loss or damage from proper use.

Two practical points follow. First, sign a dated condition record with photographs before the contractor starts, because without one the law presumes the unit was in good repair. Second, agree the reinstatement list in the approval letter itself: which items stay, which are removed, and who pays. Section 563 gives the landlord six months from the return of the property to bring a claim against the tenant under the lease, so keep the handover record at least that long. Our guides to commercial handover and the security deposit cover the money side.

11

What are the common mistakes?

  • starting demolition on an email or a verbal yes, with no signed consent that lists the drawings;
  • treating the landlord's consent as if it were the local official's permit, or the other way round;
  • signing a lease for a use the building is not permitted for;
  • finalizing the design before the electrical load and the supply are confirmed;
  • blocking or re-hanging an escape door to gain floor space;
  • leaving reinstatement to be argued at the end of the term;
  • paying the final installment before the as-built drawings, warranties and defect list are in hand.
12

What should you ask before signing or paying?

  • To the landlord: what use is the building permitted for, what are the fit-out rules and fees, how long does consent take, and what must be reinstated?
  • To the designer: is this a modification under the Building Control Act, and will you sign the notification if it is?
  • To the local office: which application applies to this scope, what does it cost today and how long does it take?
  • To the contractor: who files with the authorities, what insurance do you carry, and what do you hand over at completion?

Related commercial checklists cover lease due diligence before signing, utility capacity for the fit-out load, commercial property insurance for the completed works, and signage approval once the fit-out is ready to open. For budgeting, see construction cost benchmarks and the commercial cost estimator.

Continue through Commercial, Learn and the directory.

BAANLYY is a listing portal and does not give legal, tax or engineering advice. Thai legal texts are quoted in our own English reading. Confirm the current text and fees with the local office and your own advisers before relying on them.

Approve the full scope before mobilization.

Keep every approval and completion record with the lease.

Explore commercial property
FAQ

Frequently asked questions

Should work start before written approval?

No. Section 558 of the Civil and Commercial Code says a tenant may not alter or add to the leased property without the landlord's permission. If the tenant does, the landlord can ask for the property to be restored to its former condition, and the tenant is liable for any loss or damage the alteration causes. Get the landlord's consent in writing, with the approved drawings attached, before any contractor is on site.

Does a commercial fit-out need a building permit in Thailand?

It depends on whether the work counts as modifying the building. Section 21 of the Building Control Act B.E. 2522 says anyone who will construct, modify or move a building must obtain a permit from the local official, or notify the local official under section 39 bis. The Act defines modify as changing, adding to, increasing, reducing or enlarging the structure or other parts of an existing building so that it differs from the original, other than repairs and works a Ministerial Regulation excludes. We could not open the current text of that regulation, so ask the architect or the local office to say in writing which side of the line your scope falls on.

Who is the local official for a building permit?

The Building Control Act names the Governor of Bangkok for Bangkok, the mayor for a municipality and the Mayor of Pattaya City for Pattaya, with other local administrative heads for their own areas. In practice the application is handled by the local office for the area. A Bangkok guide we read is issued by a district office of the Bangkok Metropolitan Administration.

What if the unit will be used for a different business than before?

Check the use the building was permitted for. Under section 32 of the Building Control Act, the owner or occupier of a controlled-use building may not use it, or let anyone use it, for a business other than the one stated in the permit or notification. Section 33 requires a permit from, or a notification to, the local official before a controlled-use building is changed from one such business to another. Ask the landlord for the building's certificate and permitted use before signing.

What is the penalty for modifying a building without a permit?

Section 65 of the Building Control Act, in the text we read (amended through 2015), sets imprisonment of up to three months, a fine of up to 60,000 baht, or both, for breaching section 21, 32 or 33 among others. For section 21 and section 32 it adds a daily fine of up to 10,000 baht for as long as the breach continues.

Who owns the completed fit-out?

The Civil and Commercial Code sections we read do not answer this directly. Section 558 lets the landlord demand that an unapproved alteration be removed, and section 561 requires the property to be returned in the condition in which it was received. So the lease and the approval letter should say, item by item, what stays, what the tenant removes, who pays and by when.

Should contractors follow building rules?

Yes. Ask the landlord for the building rules on access, working hours, noise, hot work, waste removal and insurance before pricing the job. Section 562 of the Civil and Commercial Code makes a tenant liable for loss or damage caused to the leased property by the tenant's own fault, so attach the building rules to the contractor's agreement and have the contractor sign up to them too.

Is tax withheld from the fit-out contractor's invoices?

When the payer is a company or other juristic person, yes. Clause 8 of Revenue Departmental Order No. Tor Por 4/2528 says such a payer shall withhold income tax at a rate of 3.0 percent when paying income from hire of work or service to the payees it lists, which include a company incorporated under Thai law. Clause 12/7 applies the duty where the agreement value is 1,000 baht or above, even if it is paid in smaller installments.

Does a restaurant fit-out need anything extra?

Yes. Section 38 of the Public Health Act B.E. 2535 says a food-selling or food-storage place in a building or area of more than 200 square meters, and not selling in a market, needs a license from the local official. At 200 square meters or less the operator must notify the local official before setting up, in order to receive a certificate of notification. Plan the kitchen with that application in mind.

Ask a question

Didn’t find your answer above? Ask below -- real questions help us decide what to write next.

Sources & References

Sources & References

Primary and official sources are cited above. Government rules, fees and procedures in Thailand change over time and vary by office; always confirm current requirements with the relevant authority before relying on them. BAANLYY never takes paid placement in editorial content.

New to Thailand? BAANLYY can help with:
Visa helpRelocationInvesting helpCorporate housing

Have a question BAANLYY can help with?

Planning a move, a rental or an investment in Thailand? Tell us what you need, visa, housing, relocation, the numbers, and our team points you the right way. No obligation.

Add at least one way to reach you. *

Free tools for this

Start with a free tool

All Tools & Calculators